Wednesday, July 29, 2009

The underground work is ALMOST complete. There is one more storm sewer spot repair to complete on the north end of Buttonwood, but that cannot be done until a utility conflict is resolved. This will not delay any of the other work in any way.

Beginning this week, weather permitting, the contractor will start cleaning up and preparing for the roadway portion of the work, which will include driveway apron saw cutting and repairs, curb installation around the designated islands and then pavement removal. Once the pavement is removed the testing of the road base will be done and then the first course of asphalt will be installed. Access to driveways will still be available although there may be short delays during the pavement removal process.