Thursday, July 16, 2009

All water main work has been completed. The main is in and connected to any existing mains that are at the ends of the projects, all house services have been connected, and old fire hydrants have been removed.

The contractor is installing the final sanitary manhole today and then continuing with storm sewer installation. Storm sewer installation will continue next week as well. Pavement removal will not begin until all underground work has been completed.